Upgrade from CEMAT V4 to Minerals V10 in Korea

Our customers in Korea entrusted us with the migration of the CEMAT V4 control systems of two cement plants. Originally implemented in the 1990s using the CEMCASE engineering tool, these systems are now being migrated by us to the latest PCS7 CEMAT/Minerals Version 10. In the process, we are optimizing existing functionalities, integrating the new features of the Minerals package, and cleaning up the numerous “hot fixes” that were added over many years of plant operation.

Thanks to our extensive experience in migrating existing plant software, as well as the testing and acceptance procedures established at KMI, we guarantee our customers a safe and reliable commissioning – with minimal downtime and maximum future readiness.